Cloud Tower-1
Construction Updates
Foundation Pile Work
construction Progress
In Piling Process
72%
Based on our internal inspection carried out on MAY-2026, the overall piling progress has reached 72%.
MAY 2026
Cloud Tower-1 Construction Update
A total of 184 out of 246 piles have been completed. Piling works have reached 72% completion, while related site activities continue. This milestone reflects strong progress in the project’s foundation phase and overall construction schedule.