Ground Floor Slab Work

construction Progress

Overall Construction Progress 36%

Based on our internal inspection carried out on MAY-2026, the overall construction progress has reached 36%.

MAY 2026

concrete Pouring

All 3 Basements, along with the Lower Ground, have been completed. Block masonry work is in progress, while electrical wiring for the 3 basement levels has been completed.

Recently, the pouring of Columns, Shear Walls, and Lift Walls for the Ground Floor was held. Overall, 36% of the project’s structural work has been completed, while finishing work on the basement floors is also going on in parallel.

Please note that this progress status is as of May 21, our last working day on site before the Eid holidays.

Our 0% down payment Offer

*Book Studio, 1, 2 & 3 bed apartments in Islamabad with 0% down payment. Monthly installments starting from CAD 700. All NOCs issued.