Cloud Residences

construction Progress

May 2026

All 3 basements and the Lower Ground Floor are complete. Basement electrical works are finished, while masonry and finishing activities continue. Ground Floor columns, shear walls, and lift walls have been cast, bringing overall structural progress to 36%.

Please note that this progress status is as of May 21, our last working day on site before the Eid holidays.

Cloud Tower 1

construction Progress

May 2026

A total of 184 out of 246 piles have been completed. Piling works have reached 72% completion, while related site activities continue. This milestone reflects strong progress in the project’s foundation phase and overall construction schedule.

Please note that this progress status is as of May 21, our last working day on site before the Eid holidays.