Cloud Residences
construction Progress
May 2026
All 3 basements and the Lower Ground Floor are complete. Basement electrical works are finished, while masonry and finishing activities continue. Ground Floor columns, shear walls, and lift walls have been cast, bringing overall structural progress to 36%.
Please note that this progress status is as of May 21, our last working day on site before the Eid holidays.
Cloud Tower 1
construction Progress
May 2026
A total of 184 out of 246 piles have been completed. Piling works have reached 72% completion, while related site activities continue. This milestone reflects strong progress in the project’s foundation phase and overall construction schedule.
Please note that this progress status is as of May 21, our last working day on site before the Eid holidays.
Our Events
Cloud Tower-1 - Family Gala
19 April 2026
Islamabad Road Show
18 & 19 April 2026
The Gulf Hotel Bahrain
14 Feb 2026
The Torch Doha
10 Jan 2026
7th Tour of islamabad
19, 20, 21 Dec 2025
Cloud Tower-1 Road Show
06 Dec 2025
Cloud Tower-1 Launching Ceremony
22 Nov 2025
Cloud Tower-1 Launching Ceremony
9th Nov 2025
Brand Ambassador Signing Ceremony
05 Nov 2025